Set Build Pricing
1 Hollywood flat cost
Luan @ 2 / $21 ech
1x4x8 furring @ 13 / $3 ech
Wood glue @ 1 / $11 ech
¼ x ½ 18ga staples @ 1k min / $17 ech
¼ x 1 ½ 18ga staples @ 1k min / $23 ech
2in wood screws @ 129 min $11 ech
$143 rounded up $1 = $144
$144 per flat
(Glue, staples, and screws, are good for 12 flats.
$81 rounded up $1 = $82 per additional 11 flats.
12 flats = $1,046)
Paint / joint compound
$25 ave per 1 gal can
300sf ave per 1 gal can (7 flats)
$6 9’ x 12’ tarp 8 per session = $48
$36 6 roll 2in tape
Joint compound $23 (220sf 5 full flats 13 semes)
$8 4 pack sand paper
$15 4 pack sand sponge
$6 mud tray
$15 mud knife
$204 per 1-12 flats
Labor
$25hr x 8hr = $200 day
2 man crew = $400 day
2 man 1 week (5 day) = $2,000
(1 week cut/build, 1 week assemble/paint)
$4,000 for 2 weeks
Jacks
1x4s = $13
1 jack every 2 walls
6 per 12 flats
$13×12 = $156
Trucking / transportation
$100 ave per 10miles
15ft-20ft = 10mpg
15’ U-Haul = $31 per day + $1.25 per mile + $57 for insurance
2 day material load on/off
2 day set components drop off
$124 4days
20mil 2 days 40mil 4days
$50 40mil
2 gas refills = $200
Total $374
2 man 2 day day rate $800
$1,174 turck/transpo fee
Time frame
2 day purchase/pickup/unload
1 week cut / assemble
1 day delivery
1 week paint/ assemble
20’ x 30’ space needed
2-3 week min
Average project total
$6,580